Benfleet - Second phase of major gas network investment starts

    31 March 2023

    Media contacts

    Stephanie van Rosse

    mail stephanie.van-rosse@cadentgas.com

    Telephone0776 733 7343

    • The second phase of the major investment programme in Benfleet starts tomorrow
    • This next stage sees work along Kents Hill Road for the next 18 weeks

    Most of the work will be completed under temporary traffic lights; however, the start of this phase will see a road closure at the junction of High Road with Kents Hill Road.

    Stage 1:

    100m of open cut from the junction of High Road to outside 24 Kents Hill Road

    Kents Hill will be closed with two-way traffic lights on the High Road

    Access will be maintained for the Shell Garage (Entrance on High Road and exit heading North on Kents Hill Road)

    Access for residents within the closure will be from the north end of the closure.

    Stage 2:

    100m of open cut from outside of 24 Kents Hill Road to the junction of Melcombe Road

    The junction with Melcombe Road will be closed with two way traffic lights on Kents Hill Road

    For access, please follow the diversion.

    Stage 3:

    120m of insertion from the junction of Melcombe Road to the junction of Cumberland Avenue

    The junction of Cumberland Avenue will be closed with two way traffic lights on Kents Hill Road

    For access, please follow the diversion.

    Stage 4:

    100m of insertion from the junction of Cumberland Avenue to the junction of Oakfield Road

    The junction of Oakfield Road will be closed with two way traffic lights on Kents Hill Road

    For access, please follow the diversion.

    Stage 5:

    100m of insertion from the junction of Oakfield Road to the junction of Kimberley Road

    The junction of Kimberley Road will be closed with two way traffic lights on Kents Hill Road

    For access, please follow the diversion.

    Stage 6:

    150m of insertion from the junction of Kimberley Road to the junction of Clifton Avenue

    The junction of Clifton Avenue will be closed with 2 way lights on Kents Hill Road

    For access, follow diversion

    Stage 7:

    100m of insertion from the junction of Clifton Avenue to the junction of Villa Road

    There will be three way traffic lights over Kents Hill Road and Villa Road

    Stage 8:

    100m of insertion from the junction of Villa Road to the junction of Almere

    There will be three way traffic lights over Kents Hill Road and Almere

    Stage 9:

    100m of insertion from the junction of Almere to outside of the Holy Family Primary School

    There will be three way traffic lights over Kents Hill Road and Albion Road

    Stage 10:

    100m of insertion from outside of the Holy Family Primary School to the junction of Bowers Road

    The junction of Bowers Road will be closed with two way traffic lights on Kents Hill Road

    For access, please follow the diversion

    Stage 11:

    80m of insertion in Bowers Road from the junction of Kents Hill Road to the junction of Felstead Road

    This section, the junctions will be closed, with no traffic management on Kents Hill Road

    For access, please follow the diversion

    Stage 12:

    110m of insertion from the junction of Bowers Road to outside of 312 Kents Hill Road

    There will be two way traffic lights on Kents Hill Road only

    Stage 13:

    100m of insertion from outside of 312 Kents Hill Road to outside of 338 Kents Hill Road

    There will be two way traffic lights on Kents Hill Road only

    This section of works will be completed.

    First stage of Second phase of works



    Second phase of work in stages




    Cadent

    Cadent is the UK’s largest gas distribution network with a 200-year legacy. We are in a unique position to build on strong foundations whilst encouraging the curiosity to think differently and the courage to embrace change. Day to day we continue to operate, maintain and innovate the UK’s largest gas network, transporting gas safely and protecting people in an emergency. Our skilled engineers and specialists remain committed to the communities we serve, working day and night to ensure gas reaches 11 million homes from Cumbria to North London and the Welsh Borders to East Anglia, to keep your energy flowing.

    Future of Gas:

    Here at Cadent we support the Government’s plans to reach Net Zero by 2050. That means we’re backing the introduction of hydrogen as a low carbon alternative to natural gas for the future. We know people love the controllability of gas and, with our network already in place, it makes sense to switch to the lower carbon alternative offered by hydrogen, which we believe can keep homes and businesses warm for generations to come.

    Cadent manages the national gas emergency service free phone line on behalf of the gas industry - 0800 111 999*

    Cadent Gas Ltd is owned by a consortium of global investors.

    *All calls are recorded and may be monitored.

    Incident alert
    0!

    Incidents

    Phone

    Smell Gas?

    0800 111 999*

    Aa Accessibility