Our Mission to Low Emissions

    Innovation - Hammersmith Bridge project

    The challenge - to implement improvements and initiatives to reduce the environmental and social impact of the Hammersmith Bridge gas pipe diversion project.

    GO_EA-WINNER-Logo-CMYK-300DPI-23-(2).jpg

    The Project - to lay approximately 2.5km of new medium pressure gas pipe before decommissioning the existing gas pipes crossing Hammersmith Bridge. 

    What we have successfully achieved
    • Welfare Support Unit – Utilising solar panel arrays to harvest free renewable energy, consuming less than 10% biofuel, 100% rainwater harvesting and running at 100% near-silent, the unit reduces environmental and social impact on residents, stakeholders and wildlife.

      LE-Welfare-Unit-(2).jpg

    • Transition to Hydrotreated Vegetable Oil (HVO) – All site plant and machinery transitioned to biofuel reduces carbon emissions by 90%, therefore minimising impact on local air quality.
    • Electric Reinstatement Tools – A fully electric trench rammer and disc saw was trialled to demonstrate feasibility to reinstate sustainably whilst providing near-100% reduction in local carbon emissions and significant reduction in noise.
    • Recycling of Excavated Soil –  We engaged with the Local Authority and recycled excavated soil back into the trenches by filtering fine fill on-site.  This provides resource savings through reduction of traffic movements required to transport materials.
    • Use of Trench Cutter – implementation of an operational change from excavating with an excavator to a trench cutter.  The trench cutter has not only reduced fuel consumption by approximately 80%, but also machinery operating time by up to 8 hours, reducing disturbance to customers and residents.
    We started from the planning stage of the project

    Planning - At the planning stages of the project we looked at what we could do to reduce emissions and be more sustainable throughout the project.

    It was agreed to explore options to reduce the local environmental and social impacts of the project and that further initiatives could be implemented beyond usual business practice.

    Cadent along with Morrison Energy Services Ltd and Terrafirma Pipeline Ltd worked together and are committed to supporting the Government’s pledge to achieve net zero before 2050 and provided additional funding to implement the various initiatives used on site.

    Environmental Benefits and Innovation

    The Welfare Support Unit

    The welfare support unit on site provides engineers a location for their facilities to ensure it is neat on site and that staff do not need to leave site unnecessarily.

    The facilities include - a small office, kitchen, toilets and drying area.

    Support-Unit-(1).jpg

    Key Benefits
    • Carbon neutral   
    • 100% renewable energy
    • Solar powered with biofuel back-up
    • Low emissions
    • Rain harvesting
    • 97.2% recyclable

    The welfare support unit collects rainwater via raised parapets circling the roof’s edges.

    Low-Emissions-support-unit-(1).jpg

    1.  It then runs through a filtration system and to the welfare’s clean water tank.  From there, we can use it from both sinks situated in the canteen and toilet.
    2.  The welfare support unit runs predominantly on its solar panels. In the circumstance of long power use, the welfare will be assisted by HVO biofuel tank.
    3.  All elements of the welfare support unit can be monitored via a control panel to help us gauge our usage to be as efficient and sustainable as possible.
    Filtration-system.png
    Fuelling.png
    Monitoring-dial.png
    Plant and equipment
    • Excavator – runs on bio-fuel
    • Trench rammer & disc saw – fully electric  

    Electric-plant-and-equipment.png

    History - Hammersmith Bridge was closed in 2019 due to the integrity of the foundations of the bridge. 

    Cadent own and maintain the gas network in the area and have two pipes on the bridge, which supply gas to homes and businesses in Barnes, Mortlake and Putney.  We have been requested to decommission both gas pipes on Hammersmith Bridge.

    The project - Lay a new gas pipe before diverting the gas from the two pipes on Hammersmith Bridge, ensuring the gas supply to the local area is maintained at all times.

    Start date -  6 March 2023 for 12-14 months, to lay 2.5km (1.6 miles) of a new gas pipe.  Once this is completed, we will divert the gas from the two gas pipes on the bridge into the new pipe.

    Gas supplies will not be interrupted.

    The new gas pipe will laid from the junction of Station Road / Rocks Lane onto Castelnau.

    GO_EA-WINNER-Logo-CMYK-300DPI-23-(1).jpg

    We have won the Green Apple Environment Awards in 2023 for this project's innovation to reduce emissions for the diversion project.

    WHAT ARE THE GREEN APPLE AWARDS?

    The Green Apple Environment Awards were established in 1994 as an annual campaign to recognise, reward and promote environmental best practice around the world.

    The Green Apple Awards scheme was the first to be accredited as an official feeder scheme into the European Business Awards for the Environment and it is now the only official feeder scheme into the Green World Awards, which are held in a different country every year.

    Previous Green Apple Award winners have gone on to win European and World Awards, and many have taken on the status of International Green World Ambassadors by helping others around the world to help the environment.

    Cadent's submission
    A partnership between Cadent, Morrison Energy Services Ltd and Terrafirma Pipeline Ltd were commissioned to undertake a gas main reinforcement project within the London Borough of Richmond upon Thames.

    The project aim was to lay approximately 2.5km of new medium pressure gas main to help reinforcement the gas network and provide a sustainable and secure supply of gas to residents and the local community whilst implementing improvements and initiatives to reduce the environmental and social impact of the project.

    Project Achievements
    During the first three months the innovative solutions have seen (compared to baseline):

    1. 5,500 kg CO2e reduction in project emissions.
    2. 66% reduction in fuel consumption.
    3. Significant reduction in noise compared to business as usual utility projects and improvement in operational staff’s mental wellbeing.
    4. Improved security and stability of gas supply to customers.
    5. Improved relationship with local authority and stakeholders following operational teams performance and implementation of initiatives.

    Diverting the gas supply from Hammersmith Bridge by laying 2.5km of a new medium pressure gas pipe.

    Hammersmith-Bridge-original-map-1.png

    A different mindset

    Awareness - It started with our colleagues.   Having identified the potential impact the project could have on local wildlife and community, the team created a detailed briefing for the site team.

    Briefings were given to the team to improve their understanding of the local environmental hazards, including Barnes Common Nature Reserve, bats, nesting birds and water voles; and reiterating the procedures in place, should they encounter protected species.

    During construction - It was also established that a design change could reduce the environmental impact of the project.

    Instead of crossing Beverley Brook with the new gas main and removing ten mature trees and disturbing the riverbanks which had potential water vole habitats; we collaborated with the council and completed trial holes on the existing bridge structure.

    The trial holes were successful and the design was changed to a new four-tier manifold system. This meant the new gas main could be placed within the road, removing the need for tree felling and disturbance to the watercourse.

    A platform to deliver more sustainable projects

    LE-Welfare-Unit-(2).jpg
    Rocks-lane-welfare-unit.png
    Picture1-(2).jpg

    We are hoping to use the Hammersmith Bridge project as a platform to deliver more sustainable utility projects across our North London network.

    The transition to HVO fuel was a major success on the project. The initiative provided zero logistical issues whilst providing 90% reduction in fuel emissions. As well as providing environmental benefits, the operational team commented on how impressed they were with the near silent-running welfare unit team as they felt the unit really enhanced their ‘working conditions’. They were able to have meetings and breaks in a modern, hygienic, and quiet welfare unit without the drone of a diesel generator.

    Due to the success of the HVO fuel, welfare unit and project in general, we have already been having discussions with stakeholders to deliver another low-emissions project at Parliament Hill, Camden over the next 12 months. We have committed to phasing out all diesel generator welfare units across their multi-occupancy buildings workstream in London and had the first unit delivered in June 2023!

    In April 2023, we launched our ‘North London Environmental Action Plan’ along with our partners Morrisons, which explores a variety of channels to enhance sustainability and drive us towards our net zero ambitions. 